Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling, Field
Measurement and Testing Works (Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental
permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009 Monthly Environmental Monitoring & Audit Report
- JANUARY 2013 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
Feb 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 4.7 Marine Water Quality Stations for Additional DO
Monitoring
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real Time Noise Monitoring Station for Contract no.
HY/2009/19
Table
5.7 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.8 Air Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Table
5.23 Details of Waste
Disposal for Contract no. HY/2009/19
Table
8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Table
8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Table 8.3
Summary
of Environmental Inspections for Contract no. HY/2009/15
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Table 8.5 Summary
of Environmental Inspections for Contract no. HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 2.3 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix
6.2 Summary for Notification of
Exceedance
Appendix 8.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
Marine Works (at Wan Chai)
¡P
Rockfilling of HKCEC3E (East of HKCEC)
between CH290 and CH385
¡P
Dredging works for Type 2 sediment near Wan
Chai West Ferry Pier
¡P
Rockfilling at the southern part of HKCEC3E
(East of HKCEC) between CH290 and CH385 for subsequent open channel
construction
¡P
Installation of precast seawall blocks for
caisson and box culvert (Bay 10) installation
¡P
Installation of precast units including
caisson seawalls, box culvert (namely Bay10) and discharge outfall was
commenced and substantially completed
Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works
(at TST)
¡P
Rockfilling and rock protection to
cross-harbour watermains
¡P
Reinstatement works including seawall coping,
gully, drawpit and tree transplantation for the TST landfall was resumed.
¡P
Construction of transformer rectifier at new
reclaimed area was completed in reporting month and its cabling work
Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B6-1, B6-3, B6-5,
A1-2A & A1-3A, A2-3D (Stage 2), A3-3B, A3-4A, A3-5A, A3-3C and C1-4.
¡P
Mainlaying works and substantially
reinstatements in combined Zone A1-1 & A1-2, Zone A1-4 and Run-out of
Renaissance Hotel.
¡P
Mainlaying works at Zone A1-3 (CHWM).
¡P
Mainlaying works at Zone A1-2 (CHWM), Zone
A2-3D (Stage 2) and A3-3B.
¡P
Mainlaying works at Zone A3-4A and A3-5A.
¡P
Mainlaying works at Zone A3-3C.
¡P
Mainlaying and chamber construction works at
the traffic island near junction of
¡P
The preparation works (including exposure of
installed gate valve and repair of gate valve) at
¡P
Mainlaying works at Zone C1-4.
¡P
Mainlaying works for proposed sewerage system
in Zone B6-1, B6-3 (previously named B1-5A) and B6-5 (previously named B2-1)
¡P
Final cleaning, CCTV inspection and pressure
test for the 9 nos. cooling watermains 25 out of 27 sections of cooling mains
pipeline has been satisfied the pressure test.
Tunnel Works
¡P
Backfilling works on top of SCL protection
works.
¡P
Pre-bored H piling works for the proposed CWB
and altogether 10 nos. and 9 nos. of pre-bored H piles.
¡P
Pre-drilling works for CWB (Stage 2).
¡P
Ground treatment works for proposed CWB
diaphragm wall.
¡P
Plant Mobilization for diaphragm wall
construction works at Stage 2.
E&M
¡P
Full commissioning test for Cooling Water
Pumping Station P1
¡P
Site test for all E&M equipment and
facilities in Cooling Water Pumping Station P5
¡P
Modification work of PTI at
¡P
Modification work of bus station at
¡P
Breaking up the existing covered walkway footing at
¡P
Concreting the retaining wall base slab of Bay1, Bay 2 and Bay 5 at
¡P
Rectification works at bending block of cooling mains.
¡P
Backfilling at the conjunction between Tonnochy road and
¡P
E&M works and ABWFs installation at WSD Salt Water Pumping Station.
¡P
Concreting infill mass concrete at both sides and concreting 1m width x
300mm high mass for cover M.J. at Bay 9 to Bay 11 in salt water intake landside
cofferdam.
¡P
Backfilling grade 200mm rock material in the trench at Bay 6 to Bay 8 in
salt water intake landside cofferdam.
¡P
Drilling hole and installation of pipe bracket for aeration and
chlorination pipe inside salt water intake
¡P
The shafts of Intake chamber No.1 and No.2 for Bay 2A in salt water
intake seaside cofferdam were casted the 2nd layer of the horizontal struts.
¡P
Placing concrete for bend blocks btw CHS8A 150-165 at Ex-pet garden near
new Gate No.2.
¡P
Installation the shoring to trial pit of the permanent connection point
to existing DN 600 water main at
¡P
Saw cutting of southern diaphragm wall for the connection between
existing drainage and Bay 1 of box culvert N1.
¡P
Laying 1800mm dia. concrete pipe for the connection between existing
drainage and Bay 1 of box culvert N1.
¡P
Erecting formwork for concrete surround for concrete pipe.
¡P
Concreting of columns (total 6nos.) from M/F (+11.15mPD) to Observation
Deck Level (+14.65mPD) and Slab with beam between G.L.1-3/B-F on Level 2
(+7.65mPD).
¡P
Concreting of columns (total 9nos.) from Level 2 (+7.65mPD) to
Observation Deck Level (+14.65mPD).
¡P
Concreting of portion 2 for column C2C from +11.65mPD to +13.90mPD up to
Observation Deck Level (+14.65mPD).
¡P
Concreting of portion 1 for column C2E from +7.65mPD to +11.65mPD up to
Observation Deck Level (+14.65mPD).
¡P
Steel fixing and Formwork erection to Observation Deck Level at from GL
3-8 & 9-15.
¡P
Installation of concrete block wall for store room 1 and room 2 on Level
1.
¡P
Placing concrete of the final portion for precast scission seawall 2X.
¡P
TZ1 and TS2
reclamation works
¡P
Formation of
temporary seawall at TS2
¡P
Disassembly of staging platform
¡P
Pile case cutting
¡P
Sheet pile installation
¡P
Dredging
¡P
Construction of pre-cast unit in mainland
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile cap & column (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Post
¡P
Construction of dewatering well for Cut & Cover Tunnel
Real-time
Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
|
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HK/2009/01 |
WSD19 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
1 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
2 |
0 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
|
WSD9 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on
28 Jan 2012 |
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
3 |
0 |
2 |
5 |
3 |
2 |
1 |
0 |
0 |
1 |
0 |
0 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at
WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
1 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
1 |
2 |
0 |
2 |
|
Ex-WPCWA SE |
3 |
3 |
1 |
1 |
|
Total |
5 |
5 |
1 |
3 |
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Installation of precast seawall blocks at east of HKCEC.
¡P
Rockfilling at east of HKCEC near
¡P
Rockfilling at the southern part of HKCEC3E (East of HKCEC) between
CH290 and CH385 for subsequent open channel construction.
¡P
Construction of temporary open channel for diversion of existing box
culvert toward Area 7.
¡P
Installation of ELS for construction of proposed box culvert Bay 8 and
Bay 9.
¡P
Rockfilling and rock armour protection works to cross-harbour watermains.
¡P
Reinstatement works at TST seashore
¡P
Rockfilling and rock armour protection works to cross-harbour watermains
¡P
Fresh water flushing for cross-harbour watermains CHA, CHB, CHE &
CHF
¡P
Installation of Impressed Current Cathodic Protection (ICCP) system
including soil resistivity test, anode pits and transformer rectifier to CHA
and CHB
Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Works would be continued at Zone B6-1, B6-3, B6-5, A1-2 (CHWM), A2-3D
(Stage 2), A3-5A, A3-4A, A3-3B and C1-4.
¡P
Mainlaying works in Zone C1-2.
¡P
Mainlaying works in Zone C1-2 and C1-4 at
¡P
Mainlaying works for proposed sewerage system in Zone B6-1, B6-3 and
B6-5.
¡P
Mainlaying works in Zone A1-2 (CHWM) and A2-3D (Stage 2) at
¡P
Pressure test, grouting works and connection works at jacking pit in
Zone A1-2A & A1-3A of
¡P
Mainlaying works in Zone A3-4A, A3-5A and A3-3B at
¡P
Pressure test for cooling watermain (AC, AE & AF).
¡P
Pressure test for cross harbour watermains (whole length of land pipes
in Wan Chai).
Tunnel Works
¡P
Removal of remaining guide wall along
¡P
Backfilling at SCL section to the required level
¡P
Installation of pre-bored H-pile in CWB Stage 1b (from Ch80 to Ch120).
¡P
Installation of pre-bored H-pile in CWB Stage 2 under the atrium link
(from Ch120 to Ch220).
¡P
CWB diaphragm wall construction under the atrium link.
E&M Works
¡P
Full commissioning for Cooling Water Pumping Station P3 & P4
¡P
Initial commissioning for Cooling Water Pumping Stations P5
Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Complete
concreting works at the roof Level (except late cast portion) at the New Ferry
Pier.
¡P
Complete
rectification works of cooling mains and pressure test.
¡P
Continue 800MS
pipe installation inside
¡P
Complete hard
landscaping works at WSD Pumping Station
¡P
Continue
construction of Bay 1b and Bay 2a shaft construction at salt water intake
culverts.
¡P
Continue
remaining drainage works and reinstatement works along
¡P
Continue
Aeration and Chlorination pipe installation of Bay 3 to Bay 11 and Bay 19b to
Bay 24 inside Salt Water Intake Culvert.
¡P
Continue 800MS
pipe installation inside
¡P
Resume works for
the outfall pipe B connection inside DSD receiving pit and complete dye tests
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
¡P
Removal of eastern
breakwater of CBTS
Contract no. HK/2010/06 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Sheet pile installation
¡P
Dredging
¡P
Construction of pre-cast unit in mainland
¡P
Installation of pre-cast unit
Contract no. HY/2009/19- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Pos
¡P
Construction of dewatering well for Cut & Cover Tunnel
1.1.1. Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2. This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A Manual and ¡§Environmental
Monitoring and Audit Requirements¡¨ under Particular Specification Section
27.
1.1.3. This
report documents the finding of EM&A works for Environmental Permit no.
EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009 and FEP-05/356/2009 and during the period of December 2012 to January 2013. The cut-off date of reporting is at 27th
of each reporting month.
Section 1 Introduction ¡V details the scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit ¡V summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ¡V summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ¡V summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1. ¡§Wan Chai
Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass
and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and
2.1.2. The key
purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai
North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3. There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1. The
Project is located mainly in Wan Chai North,
2.2.2. The study
area encompasses existing developments along the Wan Chai,
2.2.3. The scope of the Project comprises:
¡P
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
¡P
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
¡P
Construction
of the new waterfront promenade, landscape works and the associated utility
services
¡P
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4. The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1. Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to apply
Further Environmental Permits (FEP) such that the impact monitoring stations
are sub-divided accordingly to facilitate the implementation of EM&A
programme and to streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2. The
details of individual contracts are summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1. Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2. The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Deputy Site
Agent |
Mr Andy Yu |
96484896 |
|||
Construction
Manager |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 3008 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy
Mak |
9103 2370 |
|||
Environmental
Supervisor |
Kwong
Weng Kit |
6253
3356 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor¡¦s Representative |
Mr. David Lau |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Clement
Pang |
9735
9200 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|
||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HK/2009/01, the principal
work activities in this reporting month included:
Marine Works (at
Wan Chai)
¡P
Rockfilling of HKCEC3E (East of HKCEC)
between CH290 and CH385
¡P
Dredging works for Type 2 sediment near Wan
Chai West Ferry Pier
¡P
Rockfilling at the southern part of HKCEC3E
(East of HKCEC) between CH290 and CH385 for subsequent open channel
construction
¡P
Installation of precast seawall blocks for
caisson and box culvert (Bay 10) installation
¡P
Installation of precast units including
caisson seawalls, box culvert (namely Bay10) and discharge outfall was
commenced and substantially completed
Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST)
¡P
Rockfilling and rock protection to
cross-harbour watermains
¡P
Reinstatement works including seawall coping,
gully, drawpit and tree transplantation for the TST landfall was resumed.
¡P
Construction of transformer rectifier at new
reclaimed area was completed in reporting month and its cabling work
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B6-1, B6-3, B6-5,
A1-2A & A1-3A, A2-3D (Stage 2), A3-3B, A3-4A, A3-5A, A3-3C and C1-4.
¡P
Mainlaying works and substantially
reinstatements in combined Zone A1-1 & A1-2, Zone A1-4 and Run-out of
Renaissance Hotel.
¡P
Mainlaying works at Zone A1-3 (CHWM).
¡P
Mainlaying works at Zone A1-2 (CHWM), Zone
A2-3D (Stage 2) and A3-3B.
¡P
Mainlaying works at Zone A3-4A and A3-5A.
¡P
Mainlaying works at Zone A3-3C.
¡P
Mainlaying and chamber construction works at
the traffic island near junction of
¡P
The preparation works (including exposure of
installed gate valve and repair of gate valve) at
¡P
Mainlaying works at Zone C1-4.
¡P
Mainlaying works for proposed sewerage system
in Zone B6-1, B6-3 (previously named B1-5A) and B6-5 (previously named B2-1)
¡P
Final cleaning, CCTV inspection and pressure
test for the 9 nos. cooling watermains 25 out of 27 sections of cooling mains
pipeline has been satisfied the pressure test.
Tunnel Works
¡P
Backfilling works on top of SCL protection
works.
¡P
Pre-bored H piling works for the proposed CWB
and altogether 10 nos. and 9 nos. of pre-bored H piles.
¡P
Pre-drilling works for CWB (Stage 2).
¡P
Ground treatment works for proposed CWB
diaphragm wall.
¡P
Plant Mobilization for diaphragm wall
construction works at Stage 2.
E&M
¡P
Full commissioning test for Cooling Water
Pumping Station P1
¡P
Site test for all E&M equipment and
facilities in Cooling Water Pumping Station P5
2.4.4.
For Contract no. HK/2009/02, the principal
work activities in this reporting month included:
¡P
Modification work of PTI at
¡P
Modification work of bus station at
¡P
Breaking up the existing covered walkway footing at
¡P
Concreting the retaining wall base slab of Bay1, Bay 2 and Bay 5 at
¡P
Rectification works at bending block of cooling mains.
¡P
Backfilling at the conjunction between Tonnochy road and
¡P
E&M works and ABWFs installation at WSD Salt Water Pumping Station.
¡P
Concreting infill mass concrete at both sides and concreting 1m width x
300mm high mass for cover M.J. at Bay 9 to Bay 11 in salt water intake landside
cofferdam.
¡P
Backfilling grade 200mm rock material in the trench at Bay 6 to Bay 8 in
salt water intake landside cofferdam.
¡P
Drilling hole and installation of pipe bracket for aeration and
chlorination pipe inside salt water intake
¡P
The shafts of Intake chamber No.1 and No.2 for Bay 2A in salt water
intake seaside cofferdam were casted the 2nd layer of the horizontal struts.
¡P
Placing concrete for bend blocks btw CHS8A 150-165 at Ex-pet garden near
new Gate No.2.
¡P
Installation the shoring to trial pit of the permanent connection point
to existing DN 600 water main at
¡P
Saw cutting of southern diaphragm wall for the connection between
existing drainage and Bay 1 of box culvert N1.
¡P
Laying 1800mm dia. concrete pipe for the connection between existing
drainage and Bay 1 of box culvert N1.
¡P
Erecting formwork for concrete surround for concrete pipe.
¡P
Concreting of columns (total 6nos.) from M/F (+11.15mPD) to Observation
Deck Level (+14.65mPD) and Slab with beam between G.L.1-3/B-F on Level 2
(+7.65mPD).
¡P
Concreting of columns (total 9nos.) from Level 2 (+7.65mPD) to
Observation Deck Level (+14.65mPD).
¡P
Concreting of portion 2 for column C2C from +11.65mPD to +13.90mPD up to
Observation Deck Level (+14.65mPD).
¡P
Concreting of portion 1 for column C2E from +7.65mPD to +11.65mPD up to
Observation Deck Level (+14.65mPD).
¡P
Steel fixing and Formwork erection to Observation Deck Level at from GL
3-8 & 9-15.
¡P
Installation of concrete block wall for store room 1 and room 2 on Level
1.
¡P
Placing concrete of the final portion for precast scission seawall 2X.
2.4.5.
For Contract no. HY/2009/15, the principal
work activities in this reporting month included:
¡P
TZ1 and TS2
reclamation works
¡P
Formation of
temporary seawall at TS2
2.4.6.
For Contract no. HK/2010/06, the principal
work activities in this reporting month included:
¡P
Sheet pile
installation
¡P
Dredging
¡P
Construction of
pre-cast unit in mainland
¡P
Installation of
pre-cast unit
2.4.7.
For Contract no. HY/2009/19, the principal
work activity in this reporting month included:
¡P
Road works at
¡P
Bored piling
(Land)
¡P
Pre-drilling
works for bored pile and Diaphragm wall
¡P
D-wall Construction
(North & South Section)
¡P
Guide wall
construction for D-wall / Barrette at North side
¡P
Construction
works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of
socket-H pile
¡P
Construction
works for Culvert U1
¡P
Construction of
Pile cap & column (Land)
¡P
Dismantling of
marine platform
¡P
Demolition of
parapet at IEC Link
¡P
Construction of
Pile caps & columns (Marine)
¡P
Cut & Cover
Tunnel sheet piling works and installation of King Post
¡P
Construction of
dewatering well for Cut & Cover Tunnel
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works (at
Wan Chai)
¡P
Rockfilling of HKCEC3E (East of HKCEC)
between CH290 and CH385
¡P
Dredging works for Type 2 sediment near Wan
Chai West Ferry Pier
¡P
Rockfilling at the southern part of HKCEC3E
(East of HKCEC) between CH290 and CH385 for subsequent open channel
construction
¡P
Installation of precast seawall blocks for
caisson and box culvert (Bay 10) installation
¡P
Installation of precast units including
caisson seawalls, box culvert (namely Bay10) and discharge outfall was
commenced and substantially completed
Cross-Harbour
Watermains Installation (CHA & CHB) and Marine Works (at TST)
¡P
Rockfilling and rock protection to
cross-harbour watermains
¡P
Reinstatement works including seawall coping,
gully, drawpit and tree transplantation for the TST landfall was resumed.
¡P
Construction of transformer rectifier at new
reclaimed area was completed in reporting month and its cabling work
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B6-1, B6-3, B6-5,
A1-2A & A1-3A, A2-3D (Stage 2), A3-3B, A3-4A, A3-5A, A3-3C and C1-4.
¡P
Mainlaying works and substantially
reinstatements in combined Zone A1-1 & A1-2, Zone A1-4 and Run-out of
Renaissance Hotel.
¡P
Mainlaying works at Zone A1-3 (CHWM).
¡P
Mainlaying works at Zone A1-2 (CHWM), Zone
A2-3D (Stage 2) and A3-3B.
¡P
Mainlaying works at Zone A3-4A and A3-5A.
¡P
Mainlaying works at Zone A3-3C.
¡P
Mainlaying and chamber construction works at
the traffic island near junction of
¡P
The preparation works (including exposure of
installed gate valve and repair of gate valve) at
¡P
Mainlaying works at Zone C1-4.
¡P
Mainlaying works for proposed sewerage system
in Zone B6-1, B6-3 (previously named B1-5A) and B6-5 (previously named B2-1)
¡P
Final cleaning, CCTV inspection and pressure
test for the 9 nos. cooling watermains 25 out of 27 sections of cooling mains
pipeline has been satisfied the pressure test.
Tunnel Works
¡P
Backfilling works on top of SCL protection
works.
¡P
Pre-bored H piling works for the proposed CWB
and altogether 10 nos. and 9 nos. of pre-bored H piles.
¡P
Pre-drilling works for CWB (Stage 2).
¡P
Ground treatment works for proposed CWB diaphragm
wall.
¡P
Plant Mobilization for diaphragm wall
construction works at Stage 2.
E&M
¡P
Full commissioning test for Cooling Water
Pumping Station P1
¡P
Site test for all E&M equipment and
facilities in Cooling Water Pumping Station P5
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Complete
concreting works at the roof Level (except late cast portion) at the New Ferry
Pier.
¡P
Complete
rectification works of cooling mains and pressure test.
¡P
Continue 800MS
pipe installation inside
¡P
Complete hard
landscaping works at WSD Pumping Station
¡P
Continue
construction of Bay 1b and Bay 2a shaft construction at salt water intake
culverts.
¡P
Continue
remaining drainage works and reinstatement works along
¡P
Continue
Aeration and Chlorination pipe installation of Bay 3 to Bay 11 and Bay 19b to
Bay 24 inside Salt Water Intake Culvert.
¡P
Continue 800MS
pipe installation inside
¡P
Resume works for
the outfall pipe B connection inside DSD receiving pit and complete dye tests
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
¡P
Removal of
eastern breakwater of CBTS
Contract no. HK/2010/06 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Disassembly of staging platform
¡P
Pile case cutting
¡P
Sheet pile installation
¡P
Dredging
¡P
Construction of pre-cast unit in mainland
Contract no. HY/2009/19 ¡V Central- Wan
Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Road works at
¡P
Bored piling (Land)
¡P
Pre-drilling works for bored pile and Diaphragm wall
¡P
D-wall Construction (North & South Section)
¡P
Guide wall construction for D-wall / Barrette at North side
¡P
Construction works for Box Culvert T1
¡P
Marine Piling
¡P
Construct ion of socket-H pile
¡P
Construction works for Culvert U1
¡P
Construction of Pile caps & columns (Land)
¡P
Dismantling of marine platform
¡P
Demolition of parapet at IEC Link
¡P
Construction of Pile caps & columns (Marine)
¡P
Cut & Cover Tunnel sheet piling works and installation of King Pos
¡P
Construction of dewatering well for Cut & Cover Tunnel
3.1.1. A summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project is shown in Table 3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
17 Aug 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Valid |
3.1.2. Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.3. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are
shown in Table 3.4 and Table 3.5.
Table 3.4 Cumulative Summary
of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr
2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS-1293-12 |
10 Dec
2012 |
10 Dec
2012 to 9 June 2013 |
Valid |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2013 |
Cancelled |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb 2013 |
Cancelled |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15 Mar 2013 |
Cancelled |
|
GW-RS0760-12 |
18 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Expired |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03 Feb 2013 |
Cancelled |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Cancelled |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01 Feb 2013 |
Cancelled |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Cancelled |
GW-RS1017-12 |
27 Sep 2012 |
30 Sep 2012 to 24 Mar 2013 |
Valid |
|
GW-RE0793-12 |
21 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Valid |
|
GW-RS1040-12 |
10 Oct 2012 |
13 Oct 2012 to 12 Apr 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov 2012 |
17 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1184-12 |
15 Nov 2012 |
17 Nov 2012 to 8 May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov 2012 |
21 Nov 2012 to 8 May 2013 |
Valid |
|
|
GW-RS1179-12 |
20 Nov 2012 |
22 Nov 2012 to 21 May 2013 |
Valid |
GW-RS1187-12 |
20 Nov 2012 |
27 Nov 2012 to 26 May 2013 |
Valid |
|
GW-RS1199-12 |
20 Nov 2012 |
26 Nov 2012 to 25 May 2013 |
Valid |
|
GW-RS-0052-13 |
18 Jan 2013 |
20 Jan 2013 to 19 July 2013 |
Valid |
|
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
|
Billing account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-096 |
3
Dec 2012 |
4 Dec 2012 to |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-106 |
12
Dec 2012 |
17 Dec 2012 to 16 Jan 2013 |
Expired |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition
2.6 |
Management Organization of Main Construction
Companies |
13 Apr 2010 |
Condition
2.7 |
Works
Schedule and Location Plan |
8 Apr 2010 |
Condition
2.8 |
Silt
Curtain Deployment Plan (Rev. 5) |
24 Aug 2012 |
Silt
Curtain Deployment Plan (Rev. 4) |
12 July
2012 |
|
Silt
Curtain Deployment Plan (Rev. 3) |
27 June
2012 |
|
Condition
2.9 |
Silt
Screen Deployment Plan |
19 Apr 2010 |
Silt Screen
Deployment Plan (Rev.4) |
15 Nov
2012 |
|
Conditions
2.8 and 2.9 |
Supplementary
Document on Silt Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report
on Field Testing for Silt Curtain |
26 Aug 2010 |
|
Report
on Field Testing for Silt Curtain (Rev. A) |
19 Nov 2010 |
|
Condition
2.12(d) |
Alternative
Proposal on Concurrent Dredging for Sewage Pipeline and |
15 Apr 2011 |
Condition
2.17 |
Noise
Management Plan |
23 Apr 2010 |
Condition
2.18 |
Landscape
Plan (Erection of Decorative Screen Hoarding along Construction Site around |
15 May
2010 |
Landscape
Plan (Night-time Lighting) |
22 Oct
2010 |
|
Landscape
Plan (Rev. B) |
15 Nov
2010 |
Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.4. Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HK/2009/02
under FEP-03/356/2009 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative Summary
of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2
Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0671-12 |
25 June 2012 |
17 Jul 2012 to 16 Jan 2013 |
Expired |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
|
GW-RS0996-12 |
25 Sept 2012 |
26 Sept 2012 to 25 Mar 2013 |
Valid |
|
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr 2013 |
Valid |
|
GW-RS1069-12 |
17 Oct 2012 |
19 Oct 2012 to 18 Apr 2013 |
Valid |
|
GW-RS1076-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1084-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1086-12 |
25 Oct 2012 |
28 Oct 2012 to 16 Apr 2013 |
Valid |
|
GW-RS1174-12 |
9 Nov 2012 |
11 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1158-12 |
16 Nov 2012 |
18 Nov 2012 to 16 May 2013 |
Valid |
GW-RS1167-12 |
16 Nov 2012 |
23 Nov 2012 to 21 May 2013 |
Valid |
|
GW-RS1204-12 |
9 Nov 2012 |
29 Nov 2012 to 23 May 2013 |
Valid |
|
GW-RS1272-12 |
5 Dec 2012 |
5 Dec 2012 to 26 May 2013 |
Valid |
|
GW-RS1223-12 |
27 Nov 2012 |
7 Dec 2012 to 5 June 2013 |
Valid |
|
GW-RS1228-12 |
30 Nov 2012 |
30 Nov 2012 to 29 May 2013 |
Valid |
|
GW-RE1055-12 |
30 Nov 2012 |
3 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RS1243-12 |
3 Dec 2012 |
5 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RS1245-12 |
5 Dec 2012 |
6 Dec 2012 to 5 June 2013 |
Valid |
|
|
GW-RS1363-12 |
24 Dec 2012 |
9 Jan 2013 to 7 July
2013 |
Valid |
GW-RS1381-12 |
31 Dec 2012 |
9 Jan 2013 to 7 July
2013 |
Valid |
|
GW-RS1384-12 |
31 Dec 2012 |
17 Jan 2013 to 6 July
2013 |
Valid |
|
GW-RS0061-13 |
17 Jan 2013 |
1 Feb 2013 to 31 July
2013 |
Valid |
|
GW-RS0062-13 |
17 Jan 2013 |
21 Jan 2013 to 15 July
2013 |
Valid |
|
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance
(Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance
(Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan
Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-095 |
19 Nov 2012 |
29 Nov 2012 to 28 May 2013 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/13-098 |
29 Nov
2012 |
6 Dec 2012 to 5 Jan 2013 |
Expired |
EP/MD/13-110 |
2 Jan 2013 |
6 Jan 2013 to 5 Feb 2013 |
Valid |
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
EP
Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement
Date of Construction of Marine Works |
8 April
2010 |
Condition 2.6 |
Management
Organization of Main Construction Companies |
10
April 2010 |
Condition
2.7 |
Works
Schedule and Location Plans |
8 April
2010 |
Condition
2.8 |
Silt
Curtain Deployment Plan (Revision A) |
20 April 2010 |
Silt
Curtain Deployment Plan (Revision B) |
25 May 2010 |
|
Silt
Curtain Deployment Plan (Revision C) |
14 Jun 2010 |
|
Silt
Curtain Deployment Plan (Revision H) |
15 Feb 2011 |
|
Silt
Curtain Deployment Plan (Revision I) |
17 Nov 2011 |
|
Silt
Curtain Deployment Plan (Revision J) |
15 Feb 2012 |
|
Silt
Curtain Deployment Plan (Revision K) |
3 May 2012 |
|
Silt
Curtain Deployment Plan (Revision L) |
25 Oct 2012 |
|
Silt
Curtain Deployment Plan (Revision M) |
30 Nov
2012 |
|
Condition
2.9 |
Silt
Screen Deployment Plan |
21 April 2010 |
Supplementary
Information for Existing WSD Salt Water Intakes at |
5 Oct 2010 |
|
Silt
Screen Deployment Plan (Revision B) |
15 Feb
2012 |
|
Silt
Screen Deployment Plan (Revision C) |
3 May 2012 |
|
Silt
Screen Deployment Plan (Revision D) |
10 Dec
2012 |
|
Condition
2.17 |
Noise
Management Plan |
6 May 2010 |
Condition
2.18 |
Landscape
Plan (Decorative Screen Hoarding) |
11 May 2010 |
Landscape
Plan (Control of Night Time Lighting) |
2 June 2010 |
|
Landscape
Plan (Combined Version) |
20 July 2011 |
|
Landscape
Plan (Combined Version) |
5 Aug 2011 |
|
----- |
Acknowledge
of Submission |
22 Aug 2011 |
Contract no. HY/2009/15 - Central-Wanchai
Bypass ¡V Tunnel (
3.1.5. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HY/2009/15 under EP-356/2009 are
shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
FEP-01/416/2011 |
11 Nov 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for Filling and Diaphragm Wall Works at TS4/ME4 |
GW-RS0924-12 |
31 Aug 2012 |
01 Sep 2012
to 28 Feb 2013 |
Cancelled |
GW-RS1191-12 |
26 Nov 2012 |
26 Nov 2012
to 11 May 2013 |
Valid |
|
Construction
Noise Permit (CNP) for bored pile construction at Eastern Breakwater of CBTS |
GW-RS1009-12 |
03 Oct 2012 |
03 Oct 2012
to 25 Mar 2013 |
Valid |
Construction
Noise Permit (CNP) for Removal Works at TS1 |
GW-RS0607-12 |
12
Jun 2012 |
13
Jun 2012 to 7
Dec 2012 |
Expired |
Construction Noise
Permit (CNP) for Dredging at TS2 |
GW-RS1023-12 |
05 Oct 2012 |
09 Oct 2012 to 25 Mar 2013 |
Cancelled |
GW-RS1234-12 |
28 Nov 2012 |
28 Nov 2012 to 15 May 2013 |
Valid |
|
Registration as a
Chemical Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010
to 27 Jan
2016 |
Valid |
Billing Account under Waste Disposal
Ordinance (Dumping by Vessel) |
7011761 |
03 Oct 2012 |
17 Oct 2012
to 16 Jan 2013 |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-097 |
28 Nov 2012 |
6
Dec 2012 to 5
Jun 2013 |
Cancelled |
EP/MD/13-113 |
22 Jan 2013 |
24
Jan 2013 to 23 Jul 2013 |
Valid |
|
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/13-103 |
18 Dec 2012 |
24 Dec 2012
to 23 Jan 2013 |
Cancelled |
EP/MD/13-114 |
23 Jan 2013 |
24
Jan 2013 to 23 Feb 2013 |
Valid |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and Location
Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
30 Nov 2010 |
|
Amendment for Silt Curtain Deployment Plan |
24 Feb 2011 |
Amendment for Silt Curtain Deployment Plan |
11 May 2011 |
|
Amendment for Silt Curtain Deployment Plan |
11 Sep 2012 |
|
Amendment for Silt Curtain Deployment Plan |
30 Oct 2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
19 Oct 2010 |
Amendment for Silt Screen Deployment Plan |
18 Feb 2011 |
|
Amendment for Silt Screen Deployment Plan |
15 Jun 2011 |
|
Condition 2.18 |
Proposal
for the Removal of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
8 Mar 2011 |
|
|
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
2 Aug 2011 |
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Condition 2.23 |
Noise Management Plan |
20 Oct 2010 |
Amendment for Noise Management Plan |
27 Jan 2011 |
3.1.6. Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 3.1.
Contract no. HK/2010/06 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.7. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2010/06 under EP-356/2009 are
shown in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
FEP-08/364//2009/A |
15 June 2012 |
N/A |
Valid |
|
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0012-12 |
18 June 2012 |
6 Jul 2012 to 5 Jan 2013 |
Expired |
PP-RS0001-13 |
3 Jan 2013 |
6 Jan ¡V 5 Jul 2013 |
Valid |
|
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0658-12 |
21 June 2012 |
13 Jul 2012 to 12 Jan 2013 |
Expired |
GW-RS0923-12 |
4 Sept 2012 |
15 Oct 2012 ¡V
14 Apr 2013 |
Replaced by
GW-RS0056-13 |
|
GW-RS0989-12 |
21 Sept 2012 |
6 Oct 2012 to 5 Apr 2013 |
Valid |
|
GW-RS0056-13 |
14 Jan 2013 |
16 Jan 2013
¡V 12 Jul 2013 |
Valid |
|
Billing Account under Waste Disposal
Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Water Discharge
Licence |
WT00010905-2011 |
4 November 2011 |
31 July 2016 |
Valid` |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date
of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
24 October 2011 |
Condition 2.7 |
Works Schedule and Location Plans |
11 March 2011 |
Condition 2.8 |
Revised Silt Curtain Deployment Plan |
31 Aug 2011 |
Revised Silt Curtain Deployment Plan |
22 Oct 2012 |
|
Revised Silt Curtain Deployment Plan |
26 Nov 2012 |
|
Full Silt Curtain Deployment Plan |
28 January 2013 |
|
Condition 2.9 |
Silt Screen Deployment Plan |
11 April 2011 |
Condition 2.23 |
Noise Management Plan |
11 March 2011 |
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.8. Summary of
the current status on licences and/or permits on environmental protection
pertinent for contract no. HY/2009/19 is shown in Table 3.12.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permit / Licence / Notification /
Approval |
Reference No. |
Issued Date |
Valid Period / Expiry date |
Status |
Further Environmental Permit |
FEP-07/364/2009/B |
20 Sep 2012 |
Granted |
Valid |
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Valid |
Construction Noise Permit (CNP) (For D-wall
construction) (Portion I, VII, VIII & IX) |
GW-RS0871-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
Construction Noise
Permit (CNP) (For Bored pile construction at Portion III, V) |
GW-RS0885-12 |
27-Aug-12 |
26-Feb-13 |
Cancelled |
Construction Noise
Permit (CNP) (For |
GW-RS1230-12 |
28-Nov-12 |
25-May-13 |
Valid |
Construction Noise
Permit (CNP) (For IEC) |
GW-RS0953-12 |
17-Sep-12 |
20-Mar-13 |
Cancelled |
GW-RS1210-12 |
29-Nov-12 |
28-May-13 |
Cancelled |
|
GW-RS0046-13 |
18-Jan-13 |
10-Jul-13 |
Valid |
|
Construction Noise
Permit (CNP) (For IEC Parapet Removal ¡V Loading/Unloading) |
GW-RS1065-12 |
16-Oct-12 |
20-Apr-13 |
Valid |
Discharge Licence (Land) |
WT00010093-2011 |
17 Aug 2012 |
30-Sept-16 |
Valid |
Discharge Licence (Sea) |
WT00010865-2011 |
03 Nov 2011 |
30-Nov-16 |
Valid |
C&D Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
- |
Vessel Disposal |
7013285 |
21 July 2011 |
Registered |
- |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
Registered |
- |
Dumping Permit (Type
1 ¡V |
EP/MD/13-101 |
24 Dec 2012 |
23 May 2013 |
Valid |
Dumping Permit (Type
2 ¡V Confined Marine Disposal) |
EP/MD/13-100 |
24 Dec 2012 |
23 Jan 2013 |
Expired |
Noise Monitoring Stations
4.1.1. The noise
monitoring stations for the Project are listed and shown in Table 4.1
and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Real-time Noise Monitoring
Stations
4.1.2. The
real-time noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
4.1.3.
The real-time noise monitoring at RTN2-Oil
Street Community Liaison Centre has been relocated to City Garden Electric
Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of
noise sensitive
4.1.4. As the
land-based piling and filling works- DP3 at Tin Hau had been completed on 3
September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD
Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009
since 28 November 2012.
Table 4.2 Real
Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitfield Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
Noise Monitoring
Parameters, Frequency and Duration
4.1.5. The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays. For all other time
periods, Leq (5 minutes) shall be employed for comparison with the
Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.6. Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
¡P
one
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.7. If
construction works are extended to include works during the hours of 1900 ¡V
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.8. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.9. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
4.2.1. The air
monitoring stations for the Project are listed and shown in Table 4.3 and
Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2. One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3. All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
4.2.4. For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5. High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
¡P
0.6
- 1.7 m3 per minute adjustable flow range;
¡P
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;
¡P
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable
of providing a minimum exposed area of 406 cm2;
¡P
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped
with a shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped
with a flow recorder for continuous monitoring;
¡P
provided
with a peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
¡P
easily
changeable filter; and
¡P
capable
of operating continuously for a 24-hour period.
4.2.6. Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7. A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8. An alternative non-HOKLAS
accredited laboratory was set-up
for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the
measurement procedures were
witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction
of the ER and IEC. IEC shall regularly audit to the measurement performed by
the laboratory to ensure the accuracy of measurement results.
4.2.9. Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for
odour patrol
4.2.12. Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
¡P
be
at least 16 years of age;
¡P
be
free from any respiratory illnesses; and
¡P
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
¡P
before
and during odour patrol
4.2.13. Odour
patrol shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any
odour at the concerned hours (afternoon is preferred for higher daily
temperature).
4.2.14. The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be
affected by the odour nuisance will be identified.
4.2.15. The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
¡P
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
¡P
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 -
Strong Identifiable, likely to have odour nuisance;
¡P
4 -
Extreme Severe odour, and unacceptable odour level.
4.2.16. The
findings including odour intensity, odour nature and possible odour sources,
and also the local wind speed and direction at each location will be recorded.
In addition, some relevant meteorological and tidal data such as daily average
temperature, and daily average humidity, on that surveyed day will be obtained
from the Hong Kong Observatory Station for reference. The Action and Limit
levels for odour patrol are shown in Appendix 6.1.
4.2.17. The
qualified odour patrol member has individual n-butanol thresholds complied with
the requirement of European Standard Method of Air Quality ¡V Determination of
Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80
ppb.
4.3.1. The EIA
Report has identified that the key water quality impact would be associated
with the dredging works during the construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water intakes.
The impact monitoring should be carried out during the proposed dredging works
to ensure the compliance with the water quality standards.
4.3.2. The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet
season (April ¡V September) will be effected and applied to the water quality
monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3. It is
proposed to monitor the water quality at 9 WSD salt water intakes and 14
cooling water intakes along the seafront of the
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Great Eagle Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4. Monitoring
of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried
out at WSD flushing water intakes and cooling water intakes. DO and Turbidity
are measured in-situ while SS is determined in laboratory.
4.3.5. In
association with the water quality parameters, other relevant data shall also
be measured, such as monitoring location/position, time, sampling depth, water
temperature, pH, salinity, dissolved oxygen (DO) saturation, weather
conditions, sea conditions, tidal stage, and any special phenomena and work
underway at the construction site etc.
Sampling Procedures and
Monitoring Equipment
4.3.6. The
interval between two sets of monitoring should not be less than 36 hours except
where there are exceedances of Action and/or Limit Levels, in which case the
monitoring frequency will be increased. Table 4.5 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ
measurements and water sampling should be carried out in each sampling event.
For selection of tides for in-situ measurement and water sampling, tidal range
of individual flood and ebb tides should be not less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement
and water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
2.
Turbidity should be measured in situ whereas SS
should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
4.3.7. The
instrument should be a portable, weatherproof dissolved oxygen measuring
instrument complete with cable, sensor, comprehensive operation manuals, and
use a DC power source. It should be capable of measuring:
¡P
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a
temperature of 0-45 degree Celsius
4.3.8. It should
have a membrane electrode with automatic temperature compensation complete with
a cable. Sufficient stocks of spare electrodes and cables should be available
for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI
5795A submersible stirrer with reel and cable or an approved similar
instrument).
4.3.9. Should
salinity compensation not be build-in in the DO equipment, in-situ salinity
shall be measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement
Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model
2100P or an approved similar instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and
Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position
Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ
Instruments
4.3.16. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix
4.2.
Laboratory Measurement /
Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure 4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior
Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western
of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern
of the ex-Wan Chai Public Cargo Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily
monitoring of suspended solids and 24 hour monitoring of turbidity at the
cooling water intakes (C6 and C7) shall be
conducted.
4.3.25.
The 24 hours monitoring of turbidty at the
cooling water intakes (C6 and C7) shall be established
by setting up a continuous water quality monitoring station in front of the
intakes during the dredging activities. The monitoring system include the
turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored.
4.3.27. The
proposed DO monitoring stations of the Project are shown in Table 4.7 and
Figure 4.1.
Table
4.7 Marine Water
Quality Stations for Additional DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
4.3.28.
The monitoring of dissolved oxygen are to be
carried out once per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
5.0.1. The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The monitoring
results are presented in according to the Individual Contract(s).
5.0.2. In the
reporting month, the concurrent contracts are as follows:
Contract no. HK/2009/01 ¡V
Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at
Contract no. HK/2009/02 Wan
Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai East
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
Contract no. HK/2010/06 Wan
Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line
Contract no. HY/2009/19-
Cental- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
5.0.3. The
environment monitoring schedules for reporting month and coming month are
presented in Appendix 5.1.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.1. The
proposed division of noise monitoring stations are summarized in Table
5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.2. Daytime and
evening period noise monitoring was conducted at the Harbour Road Sport Centre
in the reporting month.
5.1.3.
No action level exceedance and one limit
level exceedance was recorded at M1a on 24 January 2013. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.1.4. The noise
monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed
division of noise monitoring stations are summarized in Table 5.3
below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.5. Noise monitoring
results measured in the period of daytime and restricted hour are reviewed and
summarized. No exceedance was recorded in this reporting period. Details of
noise monitoring results and graphical presentation can be referred in Appendix 5.2
Contract no. HY/2009/19- Wan Chai Bypass Tunnal
(North Point Section) and Island Eastern Corridor Link
5.1.6. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.7.
No action level exceedance and four limit
level exceedances were recorded at M6 on 3, 8, 15, 24 January 2013. Details of
noise monitoring results and graphical presentation can be referred in Appendix 5.2
Contract no.
HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
5.2.1 As the land-based piling
and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and
confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong
Transport Section Whitfield Depot was excluded under EP-356/2009 since 28
November 2012.
5.2.2 The real-time noise
monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to
City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative
of noise sensitive
5.2.3 The major work activities
for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4
January 2012. The construction site was handed over to contractor HY/2009/19 on
31 December 2011 and the FEP-01/356/2009 was surrendered on 22 Oct 2012.
5.2.4 Non-project related limit
level exceedance was recorded in RTN2a in the reporting month.
5.2.5 Real-time
noise monitoring at FEHD Hong Kong Transport Section Whitfield Depot commenced
external wall renovation since 1 June 2012
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitfield
Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
l
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
l
RTN2 had been relocated to RTN2a since 5 Oct 2012
l
RTN1 monitoring had been finished on 28 Nov 2012
5.2.6
Details of real time noise monitoring results
and graphical presentation can be referred to Appendix 5.5.
5.3.1.
Due to extension of site boundary
by contractor of HY/2009/19, location of air monitoring station CMA1b ¡V Oil
Street Community Liaison Centre has been finely adjusted on 21 April 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.2. Air
monitoring was commenced on 1 April 2011 in response to the commencement of the
land-filling work for Contract no. HK/2009/01. The proposed divisions of air
monitoring stations are summarized in Table 5.7 below. No
exceedance was recorded in the reporting month.
Table 5.7 Air
Monitoring
Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.3. Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations are
summarized in Table 5.8 below. No exceedance was
recorded in the reporting month.
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.3.4. Air
monitoring was commenced on 15 March 2011 for the land filling work for
Contract no. HY/2009/15. The proposed division of air monitoring stations are
summarized in Table 5.9 below. No exceedance was recorded in the
reporting month.
Table
5.9 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site
Office |
Contract
no. HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern
Corridor Link
5.3.5. The
proposed division of air monitoring stations are summarized in Table 5.10
below. No exceedance was recorded in the reporting month.
Table 5.10 Air Monitoring Stations for Contract no.
HY/2009/19
Station |
Description |
CMA1b |
Oil St Community
Liaison Centre |
CMA2a |
|
5.4.1.
Due to the blockage of road access to C2 on 7 Jan 2013 during mid-flood,
the water quality monitoring was cancelled at C2 on 7 Jan 2013 during
mid-flood.
5.4.2.
Due to the blockage of road access to C5e and C5w on 7 Jan 2013 during
mid-ebb tide and on 911 and 14 Jan 2013 the sample was taken at contingency
location C5 on 7 Jan 2013 during mid-ebb and on 9, 11 and 14 Jan 2013 during
mid-flood and mid-ebb..
5.4.3.
WDII/RSS advised that the dredging works for submarine pipeline at
5.4.4.
Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no
water deterioration with respect to NPR was commenced since 7 Jan 2012 and it
was completed on 6 February 2012.
5.4.5.
Water quality monitoring at WSD10 and WSD15 was temporary suspended
while water quality monitoring at WSD9 and WSD17 was implemented with respect
to HK/2009/02 from 8 Feb 12 onwards;
5.4.6.
Water quality monitoring at C8 and C9 have been implemented with respect
to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
5.4.7.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Centre (C9) since 3 Feb 2012,
there is a fine adjustment of the sampling location of water quality monitoring
at C9 to the closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.8. With respect to the trial dredging at WCR2 was scheduled on
20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21
during this period was checked and indicated that there was no contribution due
to the trial dredging operation. Enhanced review of water quality around
WCR2 was also implemented and no deterioration in the water quality was
observed.
5.4.9. Due to the access of water monitoring station at WSD19 was blocked
by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
5.4.10. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
5.4.11.
Due to protruding rebar obstruction impacting water sampler within the inner
silt curtain frame at the water sampling point, water quality monitoring at C7
was temporarily suspended on 28 and 29 December 2012 during mid-ebb and
mid-flood.
5.4.12.
Due to the presence of obstacle within the inner silt curtain frame at
sampling point, water quality point at C7 was finely adjusted to the outside of
the inner silt curtain frame since 29 Dec 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.13. Water
monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The
proposed division of water monitoring stations are summarized in Table
5.12 below.
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
C2 |
Telecom
House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase
I |
835836.2 |
815910.0 |
C4e |
Great Eagle
Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
- The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
- WSD7 and WSD20 water
quality monitoring were temporarily suspended since 27 Apr 2012.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.15. Water
monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The
proposed division of water monitoring stations are summarized in Table
5.13 below.
5.4.16. Due to the
blockage of road access to C5e and C5w on 7 Jan 2013 during mid-ebb tide and on
9,11 and 14 Jan 2013 the sample was taken at contingency location C5 on 7 Jan
2013 during mid-ebb and on 9,11 and 14 Jan 2013during mid-flood and mid-ebb.
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
|||
WSD17 |
|
839790.3 |
817032.2 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung
Kai Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung
Kai Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from 8 Feb 2012.
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
5.4.17. Water
monitoring for Contract no. HK/2010/06 was commenced on 8 March 2011. The
proposed division of water monitoring stations are summarized in Table 5.14
below.
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom
House |
835647.9 |
815864.4 |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.4.18. As the removal of reclamation work
of TS1 at CBTS has been completed, all procedures have been rectified and
complied with the conditions set in EP-356/2009 and FEP-04/356/2009.
5.4.19.
Due to the commencement of the maintenance dredging on 10 November 2010,
water quality monitoring for Contract no. HY/2009/15 was commenced on 9
November 2010. The proposed division of water monitoring stations are
summarized in Table 5.15 below.
5.4.20.
Due to protruding rebar obstruction impacting water sampler within the inner
silt curtain frame at the water sampling point, water quality monitoring at C7
was temporarily suspended on 28 and 29 December 2012 during mid-ebb and
mid-flood.
5.4.21.
Due to the presence of obstacle within the inner silt curtain frame at
sampling point, water quality point at C7 was finely adjusted to the outside of
the inner silt curtain frame since 29 Dec 2012.
Table
5.15 Water Monitoring
Stations for Contract no. HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation
for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then
terminated since 17 May 2011.
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.4.22. Due to the
commencement of the marine bored piling on 28 Jan 2012, water quality
monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012. The
proposed division of water monitoring stations are summarized in Table 5.16 below.
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Remarks: C8 and C9 monitoring commenced on 28 Jan 2012.
5.4.23.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Center (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
5.4.24.
Due to the access of water monitoring station at WSD19 was blocked by
LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
5.4.25.
As per the meeting with the representative of Excelsior Hotel and World
Trade Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011.
5.4.26.
24 hours monitoring
of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the
24 hours turbidity monitoring and was kept in November 2011. Since the reinstating the seawall
was completed on 13 January 2012 and no any water deterioration was performed,
24 hour turbidity monitoring was then suspended on 27 January 2012.
5.4.27. Water
monitoring results measured in this reporting period are reviewed and
summarized. Details of water quality monitoring results and graphical
presentation can be referred in Appendix
5.4.
Table
5.17 Summary of Water Quality
Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HK/2009/01 |
WSD19 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C1 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
1 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
0 |
0 |
1 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring
finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C5w |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring
started on 8 Feb
2012 |
WSD21 |
0 |
0 |
0 |
2 |
0 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
|
WSD9 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
Total |
3 |
0 |
2 |
5 |
3 |
2 |
1 |
0 |
0 |
1 |
0 |
0 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9
were completed on 6 Feb 2012.
- C8 and C9 were
implemented with respect to HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 were
temporarily suspended from 27 Apr 2012
5.4.28.
Investigation found that no exceedance was related to project works. The
details of the recorded exceedances can be referred to the Section 6.4.
5.4.29.
Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon
Shelter and Ex-Public Cargo Works Area was conducted three days per week during
the reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table 5.18.
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
1 |
0 |
0 |
0 |
|
Ex-WPCWA
SW |
1 |
2 |
0 |
2 |
|
Ex-WPCWA
SE |
3 |
3 |
1 |
1 |
|
Total |
5 |
5 |
1 |
3 |
5.4.30. There were 6
action level exceedances and 8 limit level exceedances recorded in enhanced
dissolved oxygen monitoring in this reporting period.
5.4.31.
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored. Details of additional DO monitoring results
can be referred in Appendix
5.4a.
Contract no. HK/2009/01 - Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.5.1.
No Inert C&D waste was disposed and non-
inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0 |
22245.415 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
0 |
5104.5 |
N/A |
Non-inert C&D materials disposed, m3 |
47.8 |
1205.36 |
|
Non-inert C&D materials recycled, kg |
0 |
151143 |
N/A |
Chemical waste disposed, kg |
250 |
8800 |
N/A |
*Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
3567 (Bulk Volume) |
95432.2 (Bulk Volume) |
South of Cheung Chau |
* Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
52250 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3
¡V Special Treatment / Disposal contained in Geosynthetic Containers |
0 (Bulk
Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
5.5.2.
There were no marine sediment (Type 1- Open
Sea Disposal), marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal disposed in this
reporting month.
Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.5.3.
Inert C&D waste and Non-inert C&D
waste were disposed of in this reporting month. Details of the waste flow table
are summarized in Table 5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
2571.8 |
227871.18 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
39.68 |
785.59 |
SENT Landfill |
Non-inert C&D materials recycled,
m3 |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
350 |
6036 |
SENT Landfill |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
154,827 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
NIL |
117420 (Bulk
volume) |
East of Sha Chau |
Marine Sediment (Type 1 ¡V
Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) was
disposed of in this reporting month.
Contractor clarify the
dumping of Type 1 ¡V Open Sea Disposal (Dedicate Sites) in December reporting
month is 662 m3
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
5.5.4.
No Inert C&D waste and no non- inert
C&D waste were disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.21
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
65216 |
TKO137 FB |
|
Inert C&D materials recycled, m3 |
NIL |
304 |
ex-PCWA |
NIL |
111.9 |
TS4 |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal),
m3 |
2351 (Bulk Volume) |
100208 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
9680 (Bulk Volume) |
216965 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
NIL |
7,050 (Bulk Volume) |
East
of Sha Chau |
Marine sediment (Type 1 ¡V Open Sea Disposal) was disposed of in
this reporting month.
Contract no. HK/2010/06 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
5.5.5.
Inert C&D waste was disposed and there
was non-Inert C&D waste was recycled in this reporting month. Details of
the waste flow table are summarized in Table 5.22.
Table 5.22 Details
of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
517 |
11883.23 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
373.9 |
HK/2009/01 |
Non-inert C&D materials disposed, m3 |
NIL |
21.35 |
SENT |
Non-inert C&D materials recycled, kg |
2300 |
3674.5 |
Recyclers |
Chemical waste disposed, L |
0 |
600 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
3,694 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
12,297 (Bulk
Volume) |
|
There was no marine
sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal generated from dredging
for bore-piling casing in the reporting month.
Contract no. HY/2009/19 ¡VCentral-
WanChai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
5.5.6.
Inert C&D waste was disposed of and there
was non-inert C&D waste were recycled in this reporting month. Details of
the waste flow table are summarized in Table 5.23.
Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
23051.20 |
134722.35 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
1323 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
190.08 |
N/A |
Non-inert C&D materials recycled, kg |
39.72 |
229.8 |
N/A |
Chemical waste disposed, L |
NIL |
0.29 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
83 |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
182 |
664 |
|
There was no
marine sediment Type1- Open Sea Disposal and there was Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal generated from dredging for bore-piling
casing in the reporting month.
6.0.1. The Event
Action Plan for construction noise, air quality and water quality are presented
in Appendix 6.1.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.1.1 One limit level
exceedance was recorded on 24 Jan 2013 at M1a- Habour Road Sports Centre in the
reporting month. Investigation found that non- CWB project drilling works
nearby was the major noise contribution during monitoring. As such the
exceedance was not related to the Project..
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.1.1. One limit level
exceedance was recorded on 24 Jan 2013 at M1a- Habour Road Sports Centre in the
reporting month. Investigation found that non- CWB project drilling works
nearby was the major noise contribution during monitoring. As such the
exceedance was not related to the Project.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
6.1.2 No exceedance
was recorded in the reporting month.
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR
Tsuen Wan Line
6.1.3 No exceedance
was recorded in the reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.4
Four limit level
exceedances were recorded on 3, 8, 15 and 24 January 2013 at M6 ¡V
HK Baptist Church Henrietta Secondary School in the reporting month. Investigations found that major traffic
noise was contributed in the noise monitoring and exceedances were not
related to the Project..
6.2.1 No exceedance
was recorded at RTN2a during the reporting month.
6.3.1.
No exceedance was recorded in 1-hr TSP and
24-hrs TSP monitoring in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
6.4.1 There was Turbidity
exceedence at C1 recorded during flood tide on 28 Dec 2012 in this reporting
month. According to the information reported by Contractor HK/2009/01 on 28 Dec
2012, Grade 75 of Backfilling on CHWM was conducted on that day. Checking with
contractor's inspection record, the silt screen and silt curtain were in proper
condition on that day. In the view that the silt screen and silt curtain were
in proper condition, it was considered not related to Project works.
6.4.3 There was Turbidity
exceedence at C4e recorded during flood tide on 28 Dec 2012 in this reporting
month. According to the information reported by Contractor HK/2009/01 on 28 Dec
2012, Grade 75 of Backfilling on CHWM was conducted on that day. Checking with
contractor's inspection record, the silt screen and silt curtain were in proper
condition on that day. There was no further exceedance was recorded in the next
consecutive monitoring. In view
that the water quality at monitoring stations located nearest the marine work
site were well below the Action level, the silt screen and silt curtain were in
proper condition, the exceedance was considered not related to Project works.
6.4.4 There was SS
exceedence at C3 recorded during flood tide on 2 Jan 2013 in this reporting
month. According to the information reported by Contractor HK/2009/01 on 2 Jan
2013, dredging work on east bridge was conducted on that day. Checking with
contractor's inspection record, the silt screen and silt curtain were in proper
condition on that day. There was no further exceedance was recorded in the next
consecutive monitoring. In view
that the water quality at monitoring stations located nearest the marine work
site were well below the Action level, the silt screen and silt curtain were in
proper condition, it was considered not related to Project works.
6.4.5 There was
Turbidity exceedence at C1 recorded during flood tide on 31 Dec 2012 in this
reporting month. Confirmed with Contractor, there was no work conducted during
the water quality monitoring. The exceedance was considered as natural
variation or changes of water quality in the vicinity of the water quality
monitoring station and not project related.
6.4.6 There was SS
exceedence at C4 recorded during flood tide on 31 Dec 2012 in this reporting
month. Confirmed with Contractor, there was no work conducted during the water
quality monitoring. The exceedance was considered as natural variation or
changes of water quality in the vicinity of the water quality monitoring
station and not project related.
6.4.7 There was SS
exceedence at C3 recorded during flood tide on 2 Jan 2013 in this reporting
month. According to the information reported by Contractor HK/2009/01 on 2 Jan
2013, dredging work on east bridge was conducted on that day. Checking with
contractor's inspection record, the silt screen and silt curtain were in proper
condition on that day. There was no further exceedance was recorded in the next
consecutive monitoring. In view
that the water quality at monitoring stations located nearest the marine work
site were well below the Action level, the silt screen and silt curtain were in
proper condition, it was considered not related to Project works.
6.4.8 There was SS
exceedence at C4w recorded during flood tide on 2 Jan 2013 in this reporting
month. According to the information reported by Contractor HK/2009/01 on 2 Jan
2013, dredging work on east bridge was conducted on that day. Checking with
contractor's inspection record, the silt screen and silt curtain were in proper
condition on that day. There was no further exceedance was recorded in the next
consecutive monitoring. In view
that the water quality at monitoring stations located nearest the marine work
site were well below the Action level, the silt screen and silt curtain were in
proper condition, it was considered not related to Project works.
6.4.9 There was DO
exceedances at WSD19 recorded during flood tide on 18 Jan 2013. In view that
the water quality at monitoring stations located nearest the marine work site
were well below Action Level and the silt screen was in proper condition, the
exceedances were possible in relation to the changes of water quality in the
vicinity of the water quality monitoring station and not project related.
6.4.10 There was Turbidity
exceedence at C3 recorded during flood tide on 25 Jan 2013 in this reporting
month. According to the information reported by Contractor HK/2009/01 on 28 Dec
2012, Grade 75 of Backfilling on CHWM was conducted on that day. Checking with
contractor's inspection record, the silt screen and silt curtain were in proper
condition on that day. There was no further exceedance was recorded in the next
consecutive monitoring. In view
that the water quality at monitoring stations located nearest the marine work
site were well below the Action level, the silt screen and silt curtain were in
proper condition, it was considered not related to Project works.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.4.11 There was SS
exceedence at C5w recorded during flood tide on 31 Dec 2012 in this reporting
month. Confirmed with Contractor, there was no work conducted during the water
quality monitoring. The exceedance was considered as natural variation or
changes of water quality in the vicinity of the water quality monitoring
station and not project related.
6.4.12 There was
Turbidity exceedance recorded at WSD21 on 28 December 2012 during flood tide. Confirmed
with Contractor, there was no work conducted during the water quality
monitoring. The exceedance was considered as natural variation or changes of
water quality in the vicinity of the water quality monitoring station and not
project related.
6.4.13 There was
Turbidity and SS exceedance recorded at WSD21 on 31 December 2012 during flood
tide. Confirmed with Contractor, there was no work conducted during the water
quality monitoring. The exceedance was considered as natural variation or
changes of water quality in the vicinity of the water quality monitoring
station and not project related.
6.4.14 There was SS
exceedance recorded at WSD21 on 1 January 2012 during flood tide. Confirmed
with Contractor, there was no work conducted during the water quality
monitoring. The exceedance was considered as natural variation or changes of
water quality in the vicinity of the water quality monitoring station and not
project related.
6.4.15 There was DO
exceedance recorded at WSD9 on 10 Dec 2013 during flood tide. Checking with
Contractor¡¦s work, Marine Rubbish Collecting was conducted on that day. Checking
with contractor's inspection record, the silt screen and silt curtain were in
proper condition on that day. In view that The tidal was moving westward. Since
WSD9 was located at the upstream of the Project, the exceedance was considered
not related to Project works., the exceedance was possibly due to the Natural
variation or changes of water quality in the vicinity of the water quality
monitoring station
6.4.16 There was DO exceedance
during ebb tide recorded at WSD21 on 26 December 2012. Confirmed with
Contractor, there was no work conducted during the water quality monitoring.
The exceedance was considered as natural variation or changes of water quality
in the vicinity of the water quality monitoring station and not project
related.
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
6.4.17 There were
occasionally DO exceedances at Ex-WPCWA SE and Ex-WPCWA SW recorded in this
reporting month. No odour nuisance was noted during DO monitoring. After
checking with Contractor, there was no marine work undertaken at ex-WPCWA. The
exceedances were possible in relation to the accumulation of organic particles
discharge from culvert near monitoring station and considered not related to
the Projects works.
Contract no. HK/2010/06 -
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.18 There were SS
and turbidity exceedance at C2 recorded during flood tide on 28 Dec 2012 in
this reporting month. According to the information reported by Contractor
HK/2010/06 and HK/2009/01 on 28 Dec 2012, welding works and dismantling of
staging platform under HK/2010/06 and backfilling on CHWM under HK/2009/01 were
conducted on that day. Checking with the Contractor and RSS daily records from
contract no.HK/2009/01, Grade 75 of Backfilling on CHWM was conducted on that
day. Checking with the Contractor and RSS daily records from contract
no.HK/2010/06, welding works for sheet piles and dismantling of staging
platform in marine area was
conducted on that day. Checking with contractor's inspection record, the silt
screen and silt curtain were in proper condition on that day. Since no further
exceedance was recorded in the next consecutive monitoring and he silt screen
and silt curtain were in proper condition, it was considered not related to
Project works.
Contract no. HY/2009/19-
Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
6.4.19 There were
occasionally turbidity and SS exceedances at C8 recorded in this reporting
month. Confirmed with Contractor, there was no marine work conducted near C8
and C9.The exceedances were possible in relation to the accumulation of
particles discharged from outfalls near monitoring stations and not related to
project.
6.4.20 Summary
for notification of exceedances can be referred to Appendix 6.2.
6.5.1 There was no
non-compliance from the site audits in the reporting month. The observations
and recommendations made in each individual site audit session were presented
in Section 8.
6.6.1 There was
no particular action taken since no project-related non-compliance was recorded
from the site audits and environmental monitoring in the reporting month.
7.0.1. According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.2. According
to the Monthly EM&A report (December 2012) of Central Reclamation Phase
III (CRIII), filling works, building construction works
and pipe works were performed in the November 2012 reporting
month. The water quality monitoring was completed in October 2011 and no project-related
exceedance was recorded for air and noise monitoring. It can be concluded that
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activities at Reclamation
Shoreline Sub-zones under Wan Chai Development Phase II were the filling at HKCEC3E,
dredging works for Type 2 sediment near Wan Chai West Ferry Pier, Rectification works at bending block of
cooling mains and Sheet pile installation at MTR Tunnel Crossing in the reporting
month. The major environmental impact was water quality impact at,
8.0.1. During
this reporting month, weekly environmental site audits were conducted for
Contracts no. HK/2009/01,
HK/2009/02, HY/2009/15, HK/2010/06 and HY/2009/19. No non-conformance was
identified during the site audits.
8.0.2.
Four site inspections for Contract no.
HK/2009/01 was carried out on 2, 9, 17 and 23 January 2013 in reporting month.
Results of these inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary of
Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
130102_01 |
2-Jan-13 |
Dusty trail was observed on the public road which should be
cleaned up and the vehicle wheels should be washed completely when they exit
the site. (Opposite to Grand Hyatt) |
The dusty strail was cleaned. |
Completion as observed on 9 Jan 2013 |
130102_02 |
2-Jan-13 |
The chemical containers should be provided with drip tray. (Children's playground) |
The chemical containers were removed. |
Completion as observed on 9 Jan 2013 |
130109_01 |
9-Jan-13 |
The muddy trail was observed on the public road which should be
cleaned up. (Water Channel) |
The muddy trail was cleaned up. |
Completion as observed on 17 Jan 2013 |
130117_01 |
17-Jan-13 |
Chemical container was placed directly under sun shine without
drip tray. Drip tray should be provided for chemical container. (Children's playground) |
The chemical
container was removed |
Completion as observed on 23 Jan 2013 |
130117_02 |
17-Jan-13 |
Filling material at barge should be cleaned and removed to
prevent direct dropping of material into sea. ( |
The filling material was cleaned up |
Completion as observed on 23 Jan 2013 |
130123_01 |
23-Jan-13 |
Oil stain on the bare ground should be cleared up as chemical
waste(B42)(Water Channel)
|
Oil stain was removed. |
Completion as observed on 30 Jan 2013 |
130123_02 |
23-Jan-13 |
Oil drum shoud be cleared and removed or drip tray should be
provided.(B42) |
Oil drum have been removed |
Completion as observed on 30 Jan 2013 |
130123_03 |
23-Jan-13 |
Noise barrier should be proper maintained and repaired (Water Channel) |
Noise barrier was repaired |
Completion as observed on 30 Jan 2013 |
8.0.3.
Four site inspections for Contract no.
HK/2009/02 was carried out on 3, 10, 16 and 24 January 2013 during this
reporting period. The results of these inspections and outcomes are summarized
in Table 8.2.
Table 8.2 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
130103_01 |
3-Jan-13 |
Overflow of muddy water from wheel washing facility to the public
road was observed. The adequacy of the volume of the washing facility should
be reviewed and all wastewater should be treated before discharge. (WCR1) |
The condition of wheel washing facility was improved |
Completion as observed on 10 Jan 2013 |
130103_02 |
3-Jan-13 |
Tarpaulin sheet should be provided for the tranfer of sediment to
the barge (WCR1) |
The barge was removed. |
Completion as observed on 10 Jan 2013 |
130110_01 |
10-Jan-13 |
The floating debris should be removed more regularly (Eastern
temporary seawall) |
Floating debris was collected. |
Completion as observed on 16 Jan 2013 |
8.0.4.
Four site inspections for Contract no.
HY/2009/15 was carried out on 3, 8, 15 and 22 January 2013 in reporting month.
The results of these inspections and outcomes are summarized in Table
8.3.
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action
taken by Contractor |
Outcome |
|
130103_02 |
3-Jan-13 |
Drip trays
should be provided to oil buckets |
Oil
buckets were removed. |
Completion
as observed on 08 Jan 2013 |
130103_03 |
3-Jan-13 |
Muddy
bloom generation was observed at TS1 area neat TZ1 during marine vessel
passage |
No muddy
bloom was observed |
Completion
as observed on 08
Jan 2013 |
130108_02 |
8-Jan-13 |
Oil stain
should be cleared and removed as chemical waste.(Eastern breakwater, Eastern
breakwater landing step) |
Oil stains
were removed. |
Completion
as observed on 15 Jan 2013 |
130108_03 |
8-Jan-13 |
Milky
discharge observed at treatment plant outfall (Ex-pcwa) |
No milky
discharge was observed |
Completion
as observed on 15 Jan 2013. |
130115_04 |
15-Jan-13 |
Oil stain
should be cleared and removed as chemical waste.(Eastern breakwater, Eastern
breakwater landing step) |
Oil stains
were removed |
Completion
as observed on 22 Jan 2013. |
130122_01 |
22-Jan-13 |
The
embarkment of the tempoary perimeter drainage channel should be reinstated. |
The
embarkment of perimeter has been reinstated |
Completion
as observed on 28 Jan 2013. |
8.0.5.
Four site inspections for Contract no. HK/2010/06
was carried out on 31 Deaember 2012, 7, 17 and 21 January 2013 in reporting
month. The results of these inspections and outcomes are summarized in Table 8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
130107_01 |
7-Jan-12 |
The oil
stain was observed on the platform which should be cleaned and removed as
chemical waste |
The oil
stain was removed |
Completion
as observed on 17 Jan 2013 |
130117_01 |
17-Jan-12 |
Some
abunden oil drums was observed, which should be cleaned and removed( section
II) |
The oil
durms were removed |
Completion
as observed on 21 Jan 2013 |
130121_01 |
21-Jan-12 |
Oil stain
was observed on the ground which should be cleaned and removed as chemical
waste(section II) |
The oil
stain was cleaned and removed |
Completion
as observed on 28 Jan 2013 |
8.0.6.
Five site inspections for Contract no.
HY/2009/19 was carried out on 28 December 2012, 2, 9, 16 and 23 January 2013 in
reporting month. The results of these inspections and outcomes are summarized
in Table 8.5.
Table
8.5 Summary of Environmental
Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
121228_03 |
28-Dec-12 |
Sandbag or
other protective measures should be provided at marine work platform to
prevent overflow of muddy water |
Protective
measures were provided for marine work platform |
Completion
as observed on 09 Jan 2013 |
130123_01 |
23-Jan-13 |
Muddy
water was observed discharged from wastewater treatment outlet point and
muddy dispersion was observed outside silt curtain enclosure. (Culvert T
outfall) |
Wastewater
treatment plant operates in order and silt curtain was tightened |
Completion
as observed
on 30
Jan 2013 |
130123_02 |
23-Jan-13 |
Overflow
of muddy water from site boundary was observed. Reinforcement of site
boundary embarkement should be provided immediately to prevent further
overflow (Portion I opposite to
site office) |
Sanbag
with cement motar and water pump were provided to prevent overflow. |
Completion
as observed on 30
Jan 2013 |
130123_03 |
23-Jan-13 |
Muddy
water and muddy trail at site exit should be cleared ( |
Muddy
trail at exit has been cleared |
Completion
as observed on 30 Jan 2013 |
9.0.1. There was
no complaint received in this reporting month.
9.0.2. The
details of cumulative complaint log and updated summary of complaints are
presented in Appendix 9.1.
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
27 |
January 2013 |
0 |
Project-to-Date |
27 |
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2.
WDII/RSS advised that the dredging works for submarine pipeline at
10.0.3.
As the land-based piling and filling works- DP3 at Tin Hau had been
completed on 3 September 2012 and confirmed by RSS, the real-time noise
monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was
excluded under EP-356/2009 since 28 November 2012.
10.0.4.
The real-time noise monitoring at RTN2-Oil Street
Community Liaison Centre has been relocated to City Garden Electric Centre
(RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise
sensitive
10.0.5.
Water quality monitoring at WSD10 and WSD15 will be temporary suspended
while water quality monitoring at WSD9 and WSD17 were implemented with respect
to HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;
10.0.6.
Water quality monitoring at C8 and C9 have been implemented with respect
to HY/2009/19 since the marine bore
piling work started on 28 January 2012.
10.0.7.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Centre (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
10.0.8.
Due to the access of water monitoring station at WSD19 was blocked by
LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
10.0.9.
With respect
to the trial dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3, 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water
quality monitoring results at WSD21 during this period was checked and
indicated that there was no contribution due to the trial dredging
operation. Enhanced review of water quality around WCR2 was also implemented
and no deterioration in the water quality was observed.
10.0.10. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
10.0.11. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2009/01 |
¡P
Marine Works ¡P
Installation of
precast seawall blocks at east of HKCEC. ¡P
Rockfilling at
east of HKCEC near ¡P
Rockfilling at
the southern part of HKCEC3E (East of HKCEC) between CH290 and CH385 for
subsequent open channel construction. ¡P
Construction
of temporary open channel for diversion of existing box culvert toward Area 7. ¡P
Installation
of ELS for construction of proposed box culvert Bay 8 and Bay 9. ¡P
Rockfilling
and rock armour protection works to cross-harbour watermains. ¡P
Reinstatement
works at TST seashore ¡P
Rockfilling
and rock armour protection works to cross-harbour watermains ¡P
Fresh water
flushing for cross-harbour watermains CHA, CHB, CHE & CHF ¡P
Installation
of Impressed Current Cathodic Protection (ICCP) system including soil
resistivity test, anode pits and transformer rectifier to CHA and CHB ¡P
¡P
Fresh
Watermains, Cooling Watermains and Salt Watermains (On Land) ¡P
Works would be
continued at Zone B6-1, B6-3, B6-5, A1-2 (CHWM), A2-3D (Stage 2), A3-5A,
A3-4A, A3-3B and C1-4. ¡P
Mainlaying
works in Zone C1-2. ¡P
Mainlaying
works in Zone C1-2 and C1-4 at ¡P
Mainlaying
works for proposed sewerage system in Zone B6-1, B6-3 and B6-5. ¡P
Mainlaying
works in Zone A1-2 (CHWM) and A2-3D (Stage 2) at ¡P
Pressure test,
grouting works and connection works at jacking pit in Zone A1-2A & A1-3A of
¡P
Mainlaying
works in Zone A3-4A, A3-5A and A3-3B at ¡P
Pressure test
for cooling watermain (AC, AE & AF). ¡P
Pressure test
for cross harbour watermains (whole length of land pipes in Wan Chai). ¡P
Tunnel Works ¡P
Removal of
remaining guide wall along ¡P
Backfilling at
SCL section to the required level after completion of mainlaying works of cooling
mains. ¡P
Installation
of pre-bored H-pile in CWB Stage 1b (from Ch80 to Ch120). ¡P
Installation
of pre-bored H-pile in CWB Stage 2 under the atrium link (from Ch120 to
Ch220). ¡P
CWB diaphragm
wall construction under the atrium link. ¡P
¡P
¡P
E&M Works ¡P
Full
commissioning for Cooling Water Pumping Station P3 & P4 ¡P
Initial
commissioning for Cooling Water Pumping Stations P5 |
¡P
To conform the installation and setting as in
the silt screen deployment plan ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To cover the dusty material or stockpile by
impervious sheet ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
To well maintain
the mechanical equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant
that may be in intermittent use should be shut down between work periods or
should be throttled down to a minimum ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HK/2009/02 |
¡P
Complete
concreting works at the roof Level (except late cast portion) at the New
Ferry Pier. ¡P
Complete rectification works of cooling
mains and pressure test. ¡P
Continue 800MS pipe installation inside ¡P
Complete hard landscaping works at WSD
Pumping Station ¡P
Continue construction of Bay 1b and Bay 2a
shaft construction at salt water intake culverts. ¡P
Continue remaining drainage works and
reinstatement works along ¡P
Continue Aeration and Chlorination pipe
installation of Bay 3 to Bay 11 and Bay 19b to Bay 24 inside Salt Water
Intake Culvert. ¡P
Continue 800MS pipe installation inside ¡P
Resume works for the outfall pipe B
connection inside DSD receiving pit and complete dye tests |
¡P
To cover the dusty material or stockpile by
impervious sheet; ¡P
Frequency spray water on the dry dusty road
and on the surface of concrete breaking ¡P
To well maintain the mechanical equipments /
machineries to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in
the silt screen and silt curtain
deployment plan ¡P
Movable noise
barrier shall be deployed for demolition works ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Review silt screen
deployment and silt curtain deployment and resubmit associate
plans to EPD ¡P
Implement silt
screen and silt curtain in accordance with the associated plans submitted to
EPD. |
HY/2009/15 |
¡P
Removal of eastern breakwater of CBTS |
¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Implement silt
screen and silt curtain in accordance with the associated plans submitted to
EPD. |
HK/2010/06 |
¡P
Sheet pile installation ¡P
Dredging ¡P
Construction of pre-cast unit in mainland ¡P
Installation of pre-cast unit |
¡P
To conform the installation and setting as in
the silt screen and silt curtain
deployment plan ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HY/2009/19 |
¡P
Road works at ¡P
Bored piling (Land) ¡P
Pre-drilling works for bored pile and
Diaphragm wall ¡P
D-wall Construction (North & South
Section) ¡P
Guide wall construction for D-wall / Barrette
at North side ¡P
Construction works for Box Culvert T1 ¡P
Marine Piling ¡P
Construct ion of socket-H pile ¡P
Construction works for Culvert U1 ¡P
Construction of Pile caps & columns
(Land) ¡P
Dismantling of marine platform ¡P
Demolition of parapet at IEC Link ¡P
Construction of Pile caps & columns
(Marine) ¡P
Cut & Cover Tunnel sheet piling works
and installation of King Pos ¡P
Construction of dewatering well for Cut
& Cover Tunnel |
¡P
To conform the installation and setting as in
the silt screen and silt curtain
deployment plan |